News

Argyle Aircraft Rescue and Fire Fighting Building - Progress

June 2014 - This project commenced on January 27th 2014 and is currently in week 17.

All of the Ground Floor concrete slabs and walls are completed.

The roof of the Living Room, Kitchen And Workshops Area are also completed and currently we are preparing to complete the concrete frame of the building by putting in place the concrete roofs over the Apparatus Bay which holds the service vehicles and the Alarm Room which holds the officers on look out.

The walls on the Ground Floor are being rendered in preparation of the painted finishes.