The Lodge School - Progress - Phase 3

June 2014 - The Third Phase of works which include the New Pavilion and Block K are approaching finishing stages. The roof on Block K has been installed and the building is ready to receive windows and doors. The service works inside the building will be concluded shortly, and the interior wall finishes and floor finishes should be underway by month end.
The pavilion is also well underway with the roof structure 65% completed and the sheeting to commence shortly. The downstairs interior walls have been plastered and the area is ready to receive the windows. The services are approximately 75 % completed and internal partitions, ceilings and floor finishes should commence by month end. The completion of this building should be around the 8th Sept 2014 for opening of the new school year.