Argyle Aircraft Rescue & Fire Fighting Bldg - Progress

August 2014 - After 32 weeks on the project, all the ground floor and first floor walls are primed and awaiting the finish paint. All of the roofs are on and the waterproof membrane is 90% completed. Window installation started this week and will be completed in the first week of September. The floors are mainly Terrazzo and we have installed 75%. The ceiling frame and boarding are in progress and will be completed by the end of August. Tiling to the washroom walls and floors are in progress also.