Refurbishment at The Lodge School - Progress

November 2014 - The Third Phase of works which include the New Pavilion and Block K are nearing practical completion. Block K is water sealed and the landscaping and external works are in progress. The service works are closing down and a preliminary electrical inspection was conducted. The majority of the rooms upstairs have been completed with minor snag works being done.

The works in the pavilion will soon be completed. The roof is complete and all the external walls have been painted. External works and landscaping, is well underway and these works will be completed in the coming weeks. Windows and doors are all installed and the services are nearing completion.