New Headquarters - BWA - January 2015 Progress

January 2015 - Building A - Prime & 1st coat paint to all internal areas is complete. Floor and wall tiling is advancing well and is 85% complete throughout the building. Internal doors are 50% complete and snag/final decoration has commenced on 3rd floor. Ceiling grid to 3rd & 2nd floor is complete including light fittings and AC grilles. Cabinetry including vanities and counter tops is well advanced. Electrical, plumbing and AC works are progressing well on all floors. External decoration has started and is progressing well. Roof membrane is complete. Lift installation is complete.

Building B - Prime and 1st coat to internal walls is complete. Window installation is complete. Floor and wall tiling is almost complete in all areas. Ceiling grid has commenced and plumbing/electrical works are also very advanced. Manufacture and installation of cabinetry is progressing well.

Building C - Prime and 1st coat to internal walls is complete. Window installation is complete. Ceiling framework and grid has commenced. Floor and wall tiling is well advanced and electrical/plumbing works are progressing.

Building D - All render and roof sheeting are complete. Prime to internal walls and floor tiles are also complete. Window installation is complete.

Building E - All render and roof sheeting is complete. Prime and 1st coat to walls has started and electrical/plumbing works are progressing. Window installation has commenced.

Building F is a small steel structure for executive parking which has been erected on concrete columns and roof sheeting is complete.

External works for the entire site are at an advanced stage with graded levels and kerbs installed throughout most of the site. Asphalt paving has commenced and is progressing. Surface water and waste drainage is continuing to be installed as well as all utility duct work and pipes. Testing of all installed services is ongoing. Courtyard walkway and render is complete and 2no. fountains are well advanced.