June 2015 - Excavation and backfill to the new Auditorium is mostly complete. All foundations have been cast and block work has commenced. Water tank slab has been concreted and the remainder of the basement slab will be poured shortly. The Auditorium will have of a large open basement. The ground floor will provide seating for 758 persons, the 1st floor will provide seating for 164 people, a control room, male / female changing rooms and two classrooms.

The thirty-five foot water tank next to the Auditorium has been built and the slab cast. Rendering has commenced and plumbing works will follow shortly. It will provide 10,000 gallons of water for the school when complete.