Corinth Secondary School - SLU Update

March 2015 - As the works progress in Phase 1 the First Floor slab has been poured, block work completed up to roof level, reinforcement for columns and roof beams started along with formwork for columns, lintels and beams.

In the Phase 2 works, foundation to ground floor columns and frame completed including backfill, ground day deck constructed including walkway and reinforcements ongoing to pour ground floor and walkway slab.

The columns have been prepared and footings poured in the Assembly area.